Redwood Road Construction - Updated May 18, 2018

Post Date:05/07/2018

Update - May 18, 2018

 

Traffic Pattern Changes and Lane Closures

Asphalt paving and utility work continues on Redwood Road between 400 South and Lake View Terrace Road. Expect daily traffic shifts and the following lane closures:

▪Northbound traffic will be reduced to one lane Monday through Friday from 8:30 a.m. to 5 p.m.
▪Southbound traffic will be reduced to one lane Monday through Friday from 7 a.m. to 4 p.m.

Northbound traffic will be reduced to one lane Monday through Friday from 8:30 a.m. to 5 p.m.

Southbound traffic will be reduced to one lane Monday through Friday from 7 a.m. to 4 p.m.

Work hours are Monday through Friday from 7 a.m. to 7 p.m. and weekends as needed. Drive carefully and be aware of rough roadway surfaces and large construction vehicles entering/exiting the work zone.

If you have questions, contact us by calling 801-997-5682 or emailing redwoodsaratoga@utah.gov.

 

IMG 6476 RR Lane Closures 2

Lane closures and traffic shifts on Redwood Road

 

Parkway Boulevard Entrance

On Saturday, May 19, crews will pave the middle of Parkway Boulevard. Next week, concrete work will begin on extending the multiuse trail across the road. Access to and from Redwood Road will be maintained, and one-way flagging will be used as needed to allow construction vehicles to move through the work zone. Plan ahead for minor delays in this area.

Grandview Boulevard

The dual left-turn lanes will be open to traffic beginning early next week.

Traffic Information

Get up-to-date information on traffic changes and delays:

▪Download the UDOT Traffic app
▪Follow @UDOTRegionthree on Twitter
▪Visit the UDOT Traffic website

Download the UDOT Traffic app

Follow @UDOTRegionthree on Twitter

Visit the UDOT Traffic website

 

 

IMG 6517 - Parkway Blvd.

Ongoing construction at Parkway Boulevard

 

Ongoing Work (400 South to Lake View Terrace Road)

Redwood Road:

▪Asphalt paving
▪Utility work
▪Landscaping
▪Traffic signal connections
▪Traffic sign installations
▪Street light installations

Asphalt paving

Utility work

Landscaping

Traffic signal connections

Traffic sign installations

Street light installations

Parkway Boulevard - entrance:

▪Utility work
▪Concrete placement
▪Landscaping

Utility work

Concrete placement

Landscaping

Grandview Boulevard:

▪Utility work

Utility work

 

 

Upcoming Work (400 South to Lake View Terrace Road)

Redwood Road:

▪Microsurfacing (adding a protective layer to roadway)
▪Pavement striping

Microsurfacing (adding a protective layer to roadway)

Pavement striping

Parkway Boulevard - entrance:

▪Asphalt paving

Asphalt paving

 

 

IMG 6463 - Grandview Blvd. Raised Median

Left-turn lane closure on Grandview Boulevard - ends next week

 

IMG 6481 - Grandview Blvd. Raised Median

Raised median on Grandview Boulevard

 

 

***

 

What to Expect During Construction

▪Noise
▪Dust
▪Vibration
▪Lane closures
▪Lane shifts
▪One-way flagging
▪Uneven lanes
▪Rough road surfaces
▪Traffic delays
▪Steel plates on roadway
▪Trucks entering/exiting work zone

Noise

Dust

Vibration

Lane closures

Lane shifts

One-way flagging

Uneven lanes

Rough road surfaces

Traffic delays

Steel plates on roadway

Trucks entering/exiting work zone

Construction activities are weather-dependent and subject to change.

 

Hours of Operation

Daytime Hours
Monday through Friday (weekends as needed)
7 a.m. to 7 p.m.

Nighttime Hours
Sunday through Friday (Saturdays as needed)
6 p.m. to 7 a.m.

 

***

 